  SECTION 627.707. Investigation of sinkhole claims; insurer payment; nonrenewals.  


Latest version.
  • 1Upon receipt of a claim for a sinkhole loss to a covered building, an insurer must meet the following standards in investigating a claim:
    25(1) 26The insurer must inspect the policyholder’s premises to determine if there is structural damage that may be the result of sinkhole activity.
    48(2) 49If the insurer confirms that structural damage exists but is unable to identify a valid cause of such damage or discovers that such damage is consistent with sinkhole loss, the insurer shall engage a professional engineer or a professional geologist to conduct testing as provided in s. 96627.7072 97to determine the cause of the loss within a reasonable professional probability and issue a report as provided in s. 117627.7073, 118only if sinkhole loss is covered under the policy. Except as provided in subsections (4) and (6), the fees and costs of the professional engineer or professional geologist shall be paid by the insurer.
    152(3) 153Following the initial inspection of the policyholder’s premises, the insurer shall provide written notice to the policyholder disclosing the following information:
    174(a) 175What the insurer has determined to be the cause of damage, if the insurer has made such a determination.
    194(b) 195A statement of the circumstances under which the insurer is required to engage a professional engineer or a professional geologist to verify or eliminate sinkhole loss and to engage a professional engineer to make recommendations regarding land and building stabilization and foundation repair.
    238(c) 239A statement regarding the right of the policyholder to request testing by a professional engineer or a professional geologist, the circumstances under which the policyholder may demand certain testing, and the circumstances under which the policyholder may incur costs associated with testing.
    281(4)(a) 282If the insurer determines that there is no sinkhole loss, the insurer may deny the claim.
    298(b) 299If coverage for sinkhole loss is available and the insurer denies the claim without performing testing under s. 317627.7072, 318the policyholder may demand testing by the insurer under s. 328627.7072329.
    3301. 331The policyholder’s demand for testing must be communicated to the insurer in writing within 60 days after the policyholder’s receipt of the insurer’s denial of the claim.
    3582. 359The policyholder shall pay 50 percent of the actual costs of the analyses and services provided under ss. 377627.7072 378and 379627.7073 380or $2,500, whichever is less.
    3863. 387The insurer shall reimburse the policyholder for the costs if the insurer’s engineer or geologist provides written certification pursuant to s. 408627.7073 409that there is sinkhole loss.
    414(5) 415If a sinkhole loss is verified, the insurer shall pay to stabilize the land and building and repair the foundation in accordance with the recommendations of the professional engineer retained pursuant to subsection (2), with notice to the policyholder, subject to the coverage and terms of the policy. The insurer shall pay for other repairs to the structure and contents in accordance with the terms of the policy. If a covered building suffers a sinkhole loss or a catastrophic ground cover collapse, the insured must repair such damage or loss in accordance with the insurer’s professional engineer’s recommended repairs. However, if the insurer’s professional engineer determines that the repair cannot be completed within policy limits, the insurer must pay to complete the repairs recommended by the insurer’s professional engineer or tender the policy limits to the policyholder.
    552(a) 553The insurer may limit its total claims payment to the actual cash value of the sinkhole loss, which does not include underpinning or grouting or any other repair technique performed below the existing foundation of the building, until the policyholder enters into a contract for the performance of building stabilization or foundation repairs in accordance with the recommendations set forth in the insurer’s report issued pursuant to s. 621627.7073622.
    623(b) 624In order to prevent additional damage to the building or structure, the policyholder must enter into a contract for the performance of building stabilization and foundation repairs within 90 days after the insurance company confirms coverage for the sinkhole loss and notifies the policyholder of such confirmation. This time period is tolled if either party invokes the neutral evaluation process, and begins again 10 days after the conclusion of the neutral evaluation process.
    697(c) 698After the policyholder enters into the contract for the performance of building stabilization and foundation repairs, the insurer shall pay the amounts necessary to begin and perform such repairs as the work is performed and the expenses are incurred. The insurer may not require the policyholder to advance payment for such repairs. If repair covered by a personal lines residential property insurance policy has begun and the professional engineer selected or approved by the insurer determines that the repair cannot be completed within the policy limits, the insurer must complete the professional engineer’s recommended repair or tender the policy limits to the policyholder without a reduction for the repair expenses incurred.
    809(d) 810The stabilization and all other repairs to the structure and contents must be completed within 12 months after entering into the contract for repairs described in paragraph (b) unless:
    8391. 840There is a mutual agreement between the insurer and the policyholder;
    8512. 852The claim is involved with the neutral evaluation process;
    8613. 862The claim is in litigation; or
    8684. 869The claim is under appraisal or mediation.
    876(e) 877Upon the insurer’s obtaining the written approval of any lienholder, the insurer may make payment directly to the persons selected by the policyholder to perform the land and building stabilization and foundation repairs. The decision by the insurer to make payment to such persons does not hold the insurer liable for the work performed.
    931(f) 932The policyholder may not accept a rebate from any person performing the repairs specified in this section. If a policyholder receives a rebate, coverage is void and the policyholder must refund the amount of the rebate to the insurer. Any person performing the repairs specified in this section who offers a rebate commits insurance fraud punishable as a third degree felony as provided in s. 997775.082, 998s. 999775.083, 1000or s. 1002775.0841003. As used in this paragraph, the term “rebate” means a remuneration, payment, gift, discount, or transfer of any item of value to the policyholder by or on behalf of a person performing the repairs specified in this section as an incentive or inducement to obtain repairs performed by that person.
    1054(6) 1055If the insurer obtains, pursuant to s. 1062627.7073, 1063written certification that there is no sinkhole loss or that the cause of the damage was not sinkhole activity, and if the policyholder has submitted the sinkhole claim without good faith grounds for submitting such claim, the policyholder shall reimburse the insurer for 50 percent of the actual costs of the analyses and services provided under ss. 1120627.7072 1121and 1122627.7073; 1123however, a policyholder is not required to reimburse an insurer more than $2,500 with respect to any claim. A policyholder is required to pay reimbursement under this subsection only if the policyholder requested the analysis and services provided under ss. 1164627.7072 1165and 1166627.7073 1167and the insurer, before ordering the analysis under s. 1176627.7072, 1177informs the policyholder in writing of the policyholder’s potential liability for reimbursement and gives the policyholder the opportunity to withdraw the claim.
    1199(7) 1200An insurer may not nonrenew any policy of property insurance on the basis of filing of claims for sinkhole loss if the total of such payments does not equal or exceed the policy limits of coverage for the policy in effect on the date of loss, for property damage to the covered building, as set forth on the declarations page, or if the policyholder repaired the structure in accordance with the engineering recommendations made pursuant to subsection (2) upon which any payment or policy proceeds were based. If the insurer pays such limits, it may nonrenew the policy.
    1298(8) 1299The insurer may engage a professional structural engineer to make recommendations as to the repair of the structure.
History.-s. 1, ch. 92-146; s. 4, ch. 93-401; s. 19, ch. 2005-111; s. 26, ch. 2006-12; s. 25, ch. 2011-39; s. 15, ch. 2012-151.