87(2)(a) 88The affected agencies shall prepare reports as provided in this paragraph and shall submit them to the department and the applicant within 60 days after the application is determined sufficient:1181. 119The department shall prepare a report as to the impact of each proposed natural gas transmission pipeline or corridor as it relates to matters within its jurisdiction.
1462. 147Each water management district in the jurisdiction of which a proposed natural gas transmission pipeline or corridor is to be located shall prepare a report as to the impact on water resources and other matters within its jurisdiction.
1853. 186The Department of Economic Opportunity shall prepare a report containing recommendations which address the impact upon the public of the proposed natural gas transmission pipeline or corridor, based on the degree to which the proposed natural gas transmission pipeline or corridor is consistent with the applicable portions of the state comprehensive plan and other matters within its jurisdiction. The Department of Economic Opportunity may also comment on the consistency of the proposed natural gas transmission pipeline or corridor with applicable strategic regional policy plans or local comprehensive plans and land development regulations.
2784. 279The Fish and Wildlife Conservation Commission shall prepare a report as to the impact of each proposed natural gas transmission pipeline or corridor on fish and wildlife resources and other matters within its jurisdiction.
3135. 314Each local government in which the natural gas transmission pipeline or natural gas transmission pipeline corridor will be located shall prepare a report as to the impact of each proposed natural gas transmission pipeline or corridor on matters within its jurisdiction, including the consistency of the proposed natural gas transmission pipeline or corridor with all applicable local ordinances, regulations, standards, or criteria that apply to the proposed natural gas transmission pipeline or corridor, including local comprehensive plans, zoning regulations, land development regulations, and any applicable local environmental regulations adopted pursuant to s. 406403.182 407or by other means. No change by the responsible local government or local agency in local comprehensive plans, zoning ordinances, or other regulations made after the date required for the filing of the local government’s report required by this section shall be applicable to the certification of the proposed natural gas transmission pipeline or corridor unless the certification is denied or the application is withdrawn. 4726. 473The Department of Transportation shall prepare a report on the effect of the natural gas transmission pipeline or natural gas transmission pipeline corridor on matters within its jurisdiction, including roadway crossings by the pipeline. The report shall contain at a minimum:514a. 515A report by the applicant to the department stating that all requirements of the department’s utilities accommodation guide have been or will be met in regard to the proposed pipeline or pipeline corridor; and
549b. 550A statement by the department as to the adequacy of the report to the department by the applicant.
5687. 569The Department of State, Division of Historical Resources, shall prepare a report on the impact of the natural gas transmission pipeline or natural gas transmission pipeline corridor on matters within its jurisdiction.
6018. 602The commission shall prepare a report addressing matters within its jurisdiction. The commission’s report shall include its determination of need issued pursuant to s. 626403.9422627.