eLaws of Florida

  SECTION 367.031. Original certificate.  


Latest version.
  • 1Each utility subject to the jurisdiction of the commission must obtain from the commission a certificate of authorization to provide water or wastewater service. A utility must obtain a certificate of authorization from the commission prior to being issued a permit by the Department of Environmental Protection for the construction of a new water or wastewater facility or prior to being issued a consumptive use or drilling permit by a water management district. The commission shall grant or deny an application for a certificate of authorization within 90 days after the official filing date of the completed application, unless an objection is filed pursuant to ss. 107120.569 108and 109120.57, 110or the application will be deemed granted.
History.-s. 1, ch. 71-278; s. 3, ch. 76-168; s. 1, ch. 77-457; ss. 5, 25, 26, ch. 80-99; ss. 2, 3, ch. 81-318; s. 1, ch. 85-85; ss. 4, 26, 27, ch. 89-353; s. 4, ch. 91-429; s. 8, ch. 93-35; s. 183, ch. 94-356; s. 3, ch. 96-407; s. 94, ch. 96-410.