  • 1The department shall coordinate the manufacturing development approval process with participating agencies, as set forth in this section, for manufacturers that are developing or expanding in a local government that has a local manufacturing development program.
    37(1) 38The approval process must include collaboration and coordination among, and simultaneous review by, the participating agencies of applications for the following state development approvals:
    62(a) 63Wetland or environmental resource permits.
    68(b) 69Surface water management permits.
    73(c) 74Stormwater permits.
    76(d) 77Consumptive water use permits.
    81(e) 82Wastewater permits.
    84(f) 85Air emission permits.
    88(g) 89Permits relating to listed species.
    94(h) 95Highway or roadway access permits.
    100(i) 101Any other state development approval within the scope of a participating agency’s authority.
    114(2)(a) 115When filing its application for state development approval, a manufacturer shall file with the department and each participating agency proof that its development or expansion is located in a local government that has a local manufacturing development program.
    153(b) 154If a local government repeals its local manufacturing development program ordinance, a manufacturer developing or expanding in that jurisdiction remains entitled to participate in the process if the manufacturer submitted its application for a local government development approval before the effective date of repeal.
    198(3) 199At any time during the process, if a manufacturer requests that the department convene a meeting with one or more participating agencies to facilitate the process, the department shall convene a meeting that the participating agencies shall attend.
    237(a) 238The department is not required to mediate between the participating agencies and the manufacturer, but may participate as necessary to accomplish the purposes set forth in s. 26520.60(4)(f)266.
    267(b) 268The department shall not be a party to any proceeding initiated under ss. 281120.569 282and 283120.57 284that relates to approval or disapproval of an application for state development approval processed under this section.
    301(c) 302The department’s participation in a coordinated manufacturing development approval process under this section shall have no effect on its approval or disapproval of any application for economic development incentives sought under s. 334288.061 335or another incentive requiring department approval.
    341(4) 342If a participating agency determines that an application is incomplete, the participating agency shall notify the applicant and the department in writing of the additional information necessary to complete the application.
    373(a) 374Unless the deadline is waived in writing by the manufacturer, a participating agency shall provide a request for additional information to the manufacturer and the department within 20 days after the date the application is filed with the participating agency.
    414(b) 415If the participating agency does not request additional information within the 20-day period, the participating agency may not subsequently deny the application based on the manufacturer’s failure to provide additional information.
    446(c) 447Within 10 days after the manufacturer’s response to the request for additional information, a participating agency may make a second request for additional information for the sole purpose of obtaining clarification of the manufacturer’s response.
    482(5)(a) 483Unless the deadline is waived in writing by the manufacturer, each participating agency shall take final agency action on a state development approval within its authority within 60 days after a complete application is filed. The 60-day period is tolled by the initiation of a proceeding under ss. 531120.569 532and 533120.57534.
    535(b) 536A participating agency shall notify the department if the agency intends to deny a manufacturer’s application and, unless waived in writing by the manufacturer, the department shall timely convene an informal meeting to facilitate a resolution.
    572(c) 573Unless waived in writing by the manufacturer, if a participating agency does not approve or deny an application within the 60-day period, within the time allowed by a federally delegated permitting program, or, if a proceeding is initiated under ss. 613120.569 614and 615120.57, 616within 45 days after a recommended order is submitted to the agency and the parties, the state development approval within the authority of the participating agency is deemed approved. A manufacturer seeking to claim approval by default under this subsection shall notify, in writing, the clerks of both the participating agency and the department of that intent. A manufacturer may not take action based upon the default approval until such notice is received by both agency clerks.
    693(d) 694At any time after a proceeding is initiated under ss. 704120.569 705and 706120.57, 707the manufacturer may demand expeditious resolution by serving notice on an administrative law judge and all other parties to the proceeding. The administrative law judge shall set the matter for final hearing no more than 30 days after receipt of such notice. After the final hearing is set, a continuance may not be granted without the written agreement of all parties.
    768(6) 769Subsections (4) and (5) do not apply to permit applications governed by federally delegated or approved permitting programs to the extent that subsections (4) and (5) impose timeframes or other requirements that are prohibited by or inconsistent with such federally delegated or approved permitting programs.
    814(7) 815The department may adopt rules to administer this section.