529(5)(a) 530If concurrency is applied to transportation facilities, the local government comprehensive plan must provide the principles, guidelines, standards, and strategies, including adopted levels of service to guide its application.
559(b) 560Local governments shall use professionally accepted studies to evaluate the appropriate levels of service. Local governments should consider the number of facilities that will be necessary to meet level-of-service demands when determining the appropriate levels of service. The schedule of facilities that are necessary to meet the adopted level of service shall be reflected in the capital improvement element.
619(c) 620Local governments shall use professionally accepted techniques for measuring levels of service when evaluating potential impacts of a proposed development.
640(d) 641The premise of concurrency is that the public facilities will be provided in order to achieve and maintain the adopted level of service standard. A comprehensive plan that imposes transportation concurrency shall contain appropriate amendments to the capital improvements element of the comprehensive plan, consistent with the requirements of s. 691163.3177(3)692. The capital improvements element shall identify facilities necessary to meet adopted levels of service during a 5-year period. 711(e) 712If a local government applies transportation concurrency in its jurisdiction, it is encouraged to develop policy guidelines and techniques to address potential negative impacts on future development:7391. 740In urban infill and redevelopment, and urban service areas.
7492. 750With special part-time demands on the transportation system.
7583. 759With de minimis impacts.
7634. 764On community desired types of development, such as redevelopment, or job creation projects.
777(f) 778Local governments are encouraged to develop tools and techniques to complement the application of transportation concurrency such as:7961. 797Adoption of long-term strategies to facilitate development patterns that support multimodal solutions, including urban design, and appropriate land use mixes, including intensity and density.
8212. 822Adoption of an areawide level of service not dependent on any single road segment function.
8373. 838Exempting or discounting impacts of locally desired development, such as development in urban areas, redevelopment, job creation, and mixed use on the transportation system.
8624. 863Assigning secondary priority to vehicle mobility and primary priority to ensuring a safe, comfortable, and attractive pedestrian environment, with convenient interconnection to transit.
8865. 887Establishing multimodal level of service standards that rely primarily on nonvehicular modes of transportation where existing or planned community design will provide adequate level of mobility.
9136. 914Reducing impact fees or local access fees to promote development within urban areas, multimodal transportation districts, and a balance of mixed-use development in certain areas or districts, or for affordable or workforce housing.
947(g) 948Local governments are encouraged to coordinate with adjacent local governments for the purpose of using common methodologies for measuring impacts on transportation facilities.
971(h)1. 972Local governments that continue to implement a transportation concurrency system, whether in the form adopted into the comprehensive plan before the effective date of the Community Planning Act, chapter 2011-139, Laws of Florida, or as subsequently modified, must:1010a. 1011Consult with the Department of Transportation when proposed plan amendments affect facilities on the strategic intermodal system.
1028b. 1029Exempt public transit facilities from concurrency. For the purposes of this sub-subparagraph, public transit facilities include transit stations and terminals; transit station parking; park-and-ride lots; intermodal public transit connection or transfer facilities; fixed bus, guideway, and rail stations; and airport passenger terminals and concourses, air cargo facilities, and hangars for the assembly, manufacture, maintenance, or storage of aircraft. As used in this sub-subparagraph, the terms “terminals” and “transit facilities” do not include seaports or commercial or residential development constructed in conjunction with a public transit facility.
1115c. 1116Allow an applicant for a development-of-regional-impact development order, development agreement, rezoning, or other land use development permit to satisfy the transportation concurrency requirements of the local comprehensive plan, the local government’s concurrency management system, and s. 1152380.06, 1153when applicable, if:1156(I) 1157The applicant in good faith offers to enter into a binding agreement to pay for or construct its proportionate share of required improvements in a manner consistent with this subsection.
1187(II) 1188The proportionate-share contribution or construction is sufficient to accomplish one or more mobility improvements that will benefit a regionally significant transportation facility. A local government may accept contributions from multiple applicants for a planned improvement if it maintains contributions in a separate account designated for that purpose.
1235d. 1236Provide the basis upon which the landowners will be assessed a proportionate share of the cost addressing the transportation impacts resulting from a proposed development.
12612. 1262An applicant shall not be held responsible for the additional cost of reducing or eliminating deficiencies. When an applicant contributes or constructs its proportionate share pursuant to this paragraph, a local government may not require payment or construction of transportation facilities whose costs would be greater than a development’s proportionate share of the improvements necessary to mitigate the development’s impacts.1322a. 1323The proportionate-share contribution shall be calculated based upon the number of trips from the proposed development expected to reach roadways during the peak hour from the stage or phase being approved, divided by the change in the peak hour maximum service volume of roadways resulting from construction of an improvement necessary to maintain or achieve the adopted level of service, multiplied by the construction cost, at the time of development payment, of the improvement necessary to maintain or achieve the adopted level of service.
1407b. 1408In using the proportionate-share formula provided in this subparagraph, the applicant, in its traffic analysis, shall identify those roads or facilities that have a transportation deficiency in accordance with the transportation deficiency as defined in subparagraph 4. The proportionate-share formula provided in this subparagraph shall be applied only to those facilities that are determined to be significantly impacted by the project traffic under review. If any road is determined to be transportation deficient without the project traffic under review, the costs of correcting that deficiency shall be removed from the project’s proportionate-share calculation and the necessary transportation improvements to correct that deficiency shall be considered to be in place for purposes of the proportionate-share calculation. The improvement necessary to correct the transportation deficiency is the funding responsibility of the entity that has maintenance responsibility for the facility. The development’s proportionate share shall be calculated only for the needed transportation improvements that are greater than the identified deficiency.
1565c. 1566When the provisions of subparagraph 1. and this subparagraph have been satisfied for a particular stage or phase of development, all transportation impacts from that stage or phase for which mitigation was required and provided shall be deemed fully mitigated in any transportation analysis for a subsequent stage or phase of development. Trips from a previous stage or phase that did not result in impacts for which mitigation was required or provided may be cumulatively analyzed with trips from a subsequent stage or phase to determine whether an impact requires mitigation for the subsequent stage or phase.
1663d. 1664In projecting the number of trips to be generated by the development under review, any trips assigned to a toll-financed facility shall be eliminated from the analysis.
1691e. 1692The applicant shall receive a credit on a dollar-for-dollar basis for impact fees, mobility fees, and other transportation concurrency mitigation requirements paid or payable in the future for the project. The credit shall be reduced up to 20 percent by the percentage share that the project’s traffic represents of the added capacity of the selected improvement, or by the amount specified by local ordinance, whichever yields the greater credit.
17613. 1762This subsection does not require a local government to approve a development that, for reasons other than transportation impacts, is not qualified for approval pursuant to the applicable local comprehensive plan and land development regulations.
17974. 1798As used in this subsection, the term “transportation deficiency” means a facility or facilities on which the adopted level-of-service standard is exceeded by the existing, committed, and vested trips, plus additional projected background trips from any source other than the development project under review, and trips that are forecast by established traffic standards, including traffic modeling, consistent with the University of Florida’s Bureau of Economic and Business Research medium population projections. Additional projected background trips are to be coincident with the particular stage or phase of development under review.
1887(i) 1888If a local government elects to repeal transportation concurrency, it is encouraged to adopt an alternative mobility funding system that uses one or more of the tools and techniques identified in paragraph (f). Any alternative mobility funding system adopted may not be used to deny, time, or phase an application for site plan approval, plat approval, final subdivision approval, building permits, or the functional equivalent of such approvals provided that the developer agrees to pay for the development’s identified transportation impacts via the funding mechanism implemented by the local government. The revenue from the funding mechanism used in the alternative system must be used to implement the needs of the local government’s plan which serves as the basis for the fee imposed. A mobility fee-based funding system must comply with s. 2019163.31801 2020governing impact fees. An alternative system that is not mobility fee-based shall not be applied in a manner that imposes upon new development any responsibility for funding an existing transportation deficiency as defined in paragraph (h). 2056(6)(a) 2057Local governments that apply concurrency to public education facilities shall include principles, guidelines, standards, and strategies, including adopted levels of service, in their comprehensive plans and interlocal agreements. The choice of one or more municipalities to not adopt school concurrency and enter into the interlocal agreement does not preclude implementation of school concurrency within other jurisdictions of the school district if the county and one or more municipalities have adopted school concurrency into their comprehensive plan and interlocal agreement that represents at least 80 percent of the total countywide population. All local government provisions included in comprehensive plans regarding school concurrency within a county must be consistent with each other and the requirements of this part.
2173(b) 2174Local governments and school boards imposing school concurrency shall exercise authority in conjunction with each other to establish jointly adequate level-of-service standards necessary to implement the adopted local government comprehensive plan, based on data and analysis.
2210(c) 2211Public school level-of-service standards shall be included and adopted into the capital improvements element of the local comprehensive plan and shall apply districtwide to all schools of the same type. Types of schools may include elementary, middle, and high schools as well as special purpose facilities such as magnet schools.
2261(d) 2262Local governments and school boards may utilize tiered level-of-service standards to allow time to achieve an adequate and desirable level of service as circumstances warrant.
2287(e) 2288A school district that includes relocatable facilities in its inventory of student stations shall include the capacity of such relocatable facilities as provided in s. 23131013.35(2)(b)22314.f., provided the relocatable facilities were purchased after 1998 and the relocatable facilities meet the standards for long-term use pursuant to s. 23361013.202337. 2338(f)1. 2339In order to balance competing interests, preserve the constitutional concept of uniformity, and avoid disruption of existing educational and growth management processes, local governments are encouraged, if they elect to adopt school concurrency, to apply school concurrency to development on a districtwide basis so that a concurrency determination for a specific development will be based upon the availability of school capacity districtwide.
24012. 2402If a local government elects to apply school concurrency on a less than districtwide basis, by using school attendance zones or concurrency service areas:2426a. 2427Local governments and school boards shall have the burden to demonstrate that the utilization of school capacity is maximized to the greatest extent possible in the comprehensive plan and amendment, taking into account transportation costs and court-approved desegregation plans, as well as other factors. In addition, in order to achieve concurrency within the service area boundaries selected by local governments and school boards, the service area boundaries, together with the standards for establishing those boundaries, shall be identified and included as supporting data and analysis for the comprehensive plan.
2516b. 2517Where school capacity is available on a districtwide basis but school concurrency is applied on a less than districtwide basis in the form of concurrency service areas, if the adopted level-of-service standard cannot be met in a particular service area as applied to an application for a development permit and if the needed capacity for the particular service area is available in one or more contiguous service areas, as adopted by the local government, then the local government may not deny an application for site plan or final subdivision approval or the functional equivalent for a development or phase of a development on the basis of school concurrency, and if issued, development impacts shall be subtracted from the contiguous service area’s capacity totals. Students from the development may not be required to go to the adjacent service area unless the school board rezones the area in which the development occurs.
2667(g) 2668The premise of concurrency is that the public facilities will be provided in order to achieve and maintain the adopted level-of-service standard. A comprehensive plan that imposes school concurrency shall contain appropriate amendments to the capital improvements element of the comprehensive plan, consistent with the requirements of s. 2716163.3177(3)2717. The capital improvements element shall identify facilities necessary to meet adopted levels of service during a 5-year period consistent with the school board’s educational facilities plan. 2744(h)1. 2745In order to limit the liability of local governments, a local government may allow a landowner to proceed with development of a specific parcel of land notwithstanding a failure of the development to satisfy school concurrency, if all the following factors are shown to exist:2790a. 2791The proposed development would be consistent with the future land use designation for the specific property and with pertinent portions of the adopted local plan, as determined by the local government.
2822b. 2823The local government’s capital improvements element and the school board’s educational facilities plan provide for school facilities adequate to serve the proposed development, and the local government or school board has not implemented that element or the project includes a plan that demonstrates that the capital facilities needed as a result of the project can be reasonably provided.
2881c. 2882The local government and school board have provided a means by which the landowner will be assessed a proportionate share of the cost of providing the school facilities necessary to serve the proposed development.
29162. 2917If a local government applies school concurrency, it may not deny an application for site plan, final subdivision approval, or the functional equivalent for a development or phase of a development authorizing residential development for failure to achieve and maintain the level-of-service standard for public school capacity in a local school concurrency management system where adequate school facilities will be in place or under actual construction within 3 years after the issuance of final subdivision or site plan approval, or the functional equivalent. School concurrency is satisfied if the developer executes a legally binding commitment to provide mitigation proportionate to the demand for public school facilities to be created by actual development of the property, including, but not limited to, the options described in sub-subparagraph a. Options for proportionate-share mitigation of impacts on public school facilities must be established in the comprehensive plan and the interlocal agreement pursuant to s. 3067163.317773068.3069a. 3070Appropriate mitigation options include the contribution of land; the construction, expansion, or payment for land acquisition or construction of a public school facility; the construction of a charter school that complies with the requirements of s. 31061002.33(18); 3107or the creation of mitigation banking based on the construction of a public school facility in exchange for the right to sell capacity credits. Such options must include execution by the applicant and the local government of a development agreement that constitutes a legally binding commitment to pay proportionate-share mitigation for the additional residential units approved by the local government in a development order and actually developed on the property, taking into account residential density allowed on the property prior to the plan amendment that increased the overall residential density. The district school board must be a party to such an agreement. As a condition of its entry into such a development agreement, the local government may require the landowner to agree to continuing renewal of the agreement upon its expiration. 3238b. 3239If the interlocal agreement and the local government comprehensive plan authorize a contribution of land; the construction, expansion, or payment for land acquisition; the construction or expansion of a public school facility, or a portion thereof; or the construction of a charter school that complies with the requirements of s. 32891002.33(18), 3290as proportionate-share mitigation, the local government shall credit such a contribution, construction, expansion, or payment toward any other impact fee or exaction imposed by local ordinance for public educational facilities, on a dollar-for-dollar basis at fair market value. The credit must be based on the total impact fee assessed and not on the impact fee for any particular type of school. 3351c. 3352Any proportionate-share mitigation must be directed by the school board toward a school capacity improvement identified in the 5-year school board educational facilities plan that satisfies the demands created by the development in accordance with a binding developer’s agreement.
33913. 3392This paragraph does not limit the authority of a local government to deny a development permit or its functional equivalent pursuant to its home rule regulatory powers, except as provided in this part.
3425(i) 3426When establishing concurrency requirements for public schools, a local government must enter into an interlocal agreement that satisfies the requirements in ss. 3448163.3177(6)(h)13449. and 2. and 163.31777 and the requirements of this subsection. The interlocal agreement shall acknowledge both the school board’s constitutional and statutory obligations to provide a uniform system of free public schools on a countywide basis, and the land use authority of local governments, including their authority to approve or deny comprehensive plan amendments and development orders. The interlocal agreement shall meet the following requirements:35151. 3516Establish the mechanisms for coordinating the development, adoption, and amendment of each local government’s school concurrency related provisions of the comprehensive plan with each other and the plans of the school board to ensure a uniform districtwide school concurrency system.
35562. 3557Specify uniform, districtwide level-of-service standards for public schools of the same type and the process for modifying the adopted level-of-service standards.
35783. 3579Define the geographic application of school concurrency. If school concurrency is to be applied on a less than districtwide basis in the form of concurrency service areas, the agreement shall establish criteria and standards for the establishment and modification of school concurrency service areas. The agreement shall ensure maximum utilization of school capacity, taking into account transportation costs and court-approved desegregation plans, as well as other factors.
36464. 3647Establish a uniform districtwide procedure for implementing school concurrency which provides for:3659a. 3660The evaluation of development applications for compliance with school concurrency requirements, including information provided by the school board on affected schools, impact on levels of service, and programmed improvements for affected schools and any options to provide sufficient capacity;
3699b. 3700An opportunity for the school board to review and comment on the effect of comprehensive plan amendments and rezonings on the public school facilities plan; and
3726c. 3727The monitoring and evaluation of the school concurrency system.
37365. 3737A process and uniform methodology for determining proportionate-share mitigation pursuant to paragraph (h).
3750(j) 3751This subsection does not limit the authority of a local government to grant or deny a development permit or its functional equivalent prior to the implementation of school concurrency.